Sub-problem 3b: Ramps
The HCM approximate
capacities of ramp roadways come from Exhibit 25-3 in the HCM. The
capacities are a function of the number of lanes on the ramp and the ramp
free-flow speed.
The v/c ratios
suggest that two of the ramps are close to capacity during a specific time
of the day. The Route 7 EB/I-787 SB ramp is near capacity during the AM peak
hour. Observations concur with methodology’s predictions. The
characteristics of that ramp’s operation will be discussed in detail in
sub-problem 3c.
The I-787 NB/Route
7 WB ramp is near capacity in the PM peak hour. We discovered two problems
with this ramp. One relates to the weaving section, as we found in analyzing
Location E in sub-problem 3a. The other relates to this new finding. In
sub-problem 3a, we demonstrated that the I-787 NB flows created LOS F in the
weaving section leading to this ramp. This ramp will be analyzed further in
this sub-problem when we proceed with the merging analysis.
[