Sub-problem 1d - Page 4 of 4 |
|
Sub-problem 3d:
Collector/Distributor Road
Discussion
So what lessons have we learned from the analysis? First, we encountered
another situation where the highway geometrics are non-standard from the
perspective of the HCM; so we need to determine how the situation should be
analyzed. Second, a weaving analysis is possible and appropriate between the
loop ramps, provided more-than-normal care is taken in examining and
interpreting the results of the analysis. Third, the computed number of
lanes required for an unconstrained weave needs to be compared with the
number of lanes available, realizing that the non-weaving movements are
effectively zero. This means that if the weaving movements are acceptable,
the entire weaving section is also acceptable.
[
Back ] [
Continue ] to Problem 4