Problem 6: Other
Intersection Configurations for Okeechobee Road
Printable Version
The previous two problems in this case study assumed that the
intersection of Krome Avenue and Okeechobee Road would retain the form of a
conventional at-grade intersection. This final problem examines two
alternative intersection configurations:
Sub-problem 6a:
Here we will consider the feasibility of conversion to a roundabout, using the
analysis procedures suggested in HCM Chapter 17.
Sub-problem 6b: Here we will examine
the effects of removing the high volume conflict points by the installation
of a grade-separated flyover.
This problem
differs from the previous five problems in the sense that the alternative
configurations were not actually included in the study performed for the
operating agency. The operating agency was able to rule out any interest in
either of the alternative configurations based on criteria other than
capacity considerations. So, Problem 6 is more or less hypothetical in
nature. It is included in this case study to illustrate how the HCM
procedures might be applied if there were an interest in constructing either
a roundabout or a flyover at this location.
Discussion:
Consider
the scenarios that will be analyzed in this problem. Take a few minutes to
consider constraints that may have excluded these alternatives from further
analysis by the operating agency. When you are ready to continue, click the
link below to proceed.
[
Back ] to
sub-problem 5c [
Continue ] to Sub-problem 6a |
Page Break
Sub-problem 6a:
Feasibility of Conversion to a Roundabout Step 1.
Setup
Roundabouts have become an
increasingly popular intersection treatment in the United States. By their
nature, roundabouts reduce the number of conflicts between competing movements
at intersections. Recognizing this, the 2000 edition of the HCM includes a
section in Chapter 17, identified as Part C, that addresses the capacity of
roundabouts. The procedures in that section will be applied here to
illustrate their details. Note that the HCM procedures address only the
capacity of a roundabout, which is only one element that must be considered
in establishing the suitability of this treatment alternative. No advice is
given in the HCM on other factors that could influence the suitability
issue.
The HCM section on
roundabouts begins by acknowledging the limited scope of the procedures. The
limitations include:
|
Only single lane roundabouts are covered in the chapter.
The HCM suggests that
a comprehensive roundabout analysis model should be used if capacity
values are required for multiple-lane roundabouts. |
|
The results of the computations are limited to capacity
estimates. No delay or level of service values are produced. |
|
The procedure is not recommended for cases where the
circulating flow exceeds 1,200 vph at any entry point. |
|
While the HCM procedures for other facilities produce
unique deterministic capacity results, the roundabout analysis procedures
only give a range of capacity values. |
|
While it is acknowledged that more complex traffic
interactions exist, each entry point to the roundabout is treated as an
independent junction using a simple gap acceptance model.
|
The HCM also
advises that caution is necessary in the interpretation of the results
produced by these models because their internal assumptions and parameters
have not been well validated in the United States. It further suggests that
the procedures should be used with care until additional research is
conducted. Heeding that advice, we will limit our investigation to one
simple question: “Would a single lane roundabout be able to accommodate the
projected traffic volumes at this location?”
Discussion:
Carefully
read the limitations of the HCM roundabout analysis procedure listed above.
Take a few minutes to consider these limitations. Click continue when you
are ready to proceed.
[
Back ] to Problem 6 [
Continue ] with Sub-Problem 6a |
Page Break
Sub-problem 6a:
Feasibility of Conversion to a Roundabout
Step 2: Results
|
Exhibit 3-42. Junction Conflict Points for a
3-legged Roundabout |
The following steps are
included in the HCM roundabout analysis procedure:
-
Define the layout,
identify the junctions at which conflicts occur and determine the traffic
volumes entering at each junction. Since this is a three legged
intersection, the
junctions will be configured as shown in the box at the right
-
Determine the
conflicting (circulating) volume opposing the entry at each junction. If
the circulating flow exceeds 1,200 vph, this procedure should not be used
unless field data have been collected for the
critical gap and
follow-up
time.
-
Determine the capacity
of the entry lanes using the same equation that was given in the chapter
for TWSC potential capacity. The critical gaps and follow up times are
adjusted downward to reflect the fact that a roundabout entrance is
generally designed to facilitate the entry of traffic into the circulatory
roadway.
-
Assess the general
performance of the roundabout on the basis of the
v/c ratio.
[
Back ] [ Continue ] with Sub-Problem 6a |
Page Break
Sub-problem 6a:
Feasibility of Conversion to a Roundabout
The traffic volumes at a
three-legged roundabout are much easier to compute than those at a
four-legged roundabout, because of the non-existent movements. The
computations will be simplified even further here because of the existing
channelization that effectively removes the EB and NB right turns from the
operation. Assuming no U-turns, Exhibit 3-43 shows the computed entry
and circulating volumes at each entry point.
Exhibit 3-43. Roundabout Entry and Circulating
Volumes |
Entry Point |
Entry Volume |
Circulating
Volume |
Eastbound approach |
EB Through (2,010) |
WB Left (120) |
Northbound approach |
Northbound Left
(257) |
EB Through (2,010) |
Westbound approach |
WB Through + WB Left
(358 + 120 = 478) |
NB Left (257) |
At this point it is clear
that the circulating volume, 2,010 vph, opposing the traffic entering on the
northbound approach exceeds the stated upper limit of 1,200 vph. We will
therefore abandon the HCM analysis at this point with the conclusion that
the HCM is not able to provide an indication that a single-lane roundabout
could accommodate the traffic.
This does not in itself
indicate that a roundabout should be conclusively dismissed as a legitimate
method of accommodating traffic at this intersection. It simply demonstrates
that the HCM is not able to confirm that a single-lane roundabout would be a
feasible solution to the problem. A more comprehensive roundabout
feasibility study, probably involving a multi-lane roundabout, would be
required for the operating agency if they were to pursue the notion of a
roundabout at this location. Outside of the HCM, a very good sourcebook for
conducting this type of analysis is
Roundabouts: An Informational Guide.
[
Back ] [ Continue ] to
Sub-Problem 6b |
Page Break
Sub-problem 6b:
Consideration of a Grade-Separated Flyover
Step 1. Setup
It was demonstrated in
Problem 5 that signalization would provide adequate capacity for the
projected traffic volumes at this intersection, but v/c ratios would
approach 90% and delays would be well into the LOS E range, especially for
the minor movements. Further improvements are likely to require the
elimination of conflicting movements by means of grade separation.
The HCM considers
competing movements that are grade separated to be conflict-free. Therefore
an HCM analysis of the benefits of a grade separation will usually involve
the elimination of movements from the intersection.
Consider:
|
What additional
data should be gathered to determine whether grade separation is
appropriate? |
|
What conflicting movements might benefit from grade
separation? |
Discussion:
Take
a few minutes to consider these questions. Click continue when you are ready
to proceed.
[
Back ] to Sub-problem 6a [
Continue ] with Sub-Problem 6b |
Page Break
Sub-problem 6b:
Consideration of a Grade-Separated Flyover
What
additional data should be gathered to determine whether grade separation
is appropriate? In this
limited review of the intersection we have only completed an analyses of
questions related to capacity and performance for the peak hour.
Justification for a grade-separated flyover must consider the traffic
conditions during other hours of the day. Other data such as crash history
should be gathered to determine the extent that safety considerations can
justify the construction of the facility. Finally, other users such as
pedestrians and cyclists should also be considered to determine the extent
that a grade-separated flyover affects the connectivity and safety of
these modes.
What conflicting movements might benefit from grade
separation?
There are three crossing
conflict points associated with this intersection:
|
EB through (2,010 vph) vs. NB left (257 vph) |
|
EB through (2,010 vph) vs. WB left (120 vph) |
|
NB left (257 vph) vs. WB left (120 vph) |
The most critical conflict clearly involves the eastbound through vs.
northbound left-turn movements. A grade-separated flyover for the northbound
traffic would eliminate this conflict as well as the conflict between the
northbound left-turn and westbound left-turn movements. It would also convert
the conflict between the northbound left and westbound through traffic from
a crossing conflict to a merging conflict. Recognizing that other
grade-separated interchange configurations are possible, we will use the
northbound flyover in this sub-problem to illustrate the use of the HCM in
assessing the benefits of a proposed grade separation.
[
Back ] [
Continue ] with Sub-Problem 6b |
Page Break
Sub-problem 6b:
Consideration of a Grade-Separated Flyover
|
Exhibit 3-44. Conflict Points with Right turns
removed |
Step 2: Results
The flyover eliminates all
of the critical conflict points and leaves us with only three conflict
points as illustrated in Exhibit 3-44. We will consider these
conflict points separately:
-
EB
through vs. WB Left: This conflict was examined as a separate conflict
point with TWSC operation in Sub-problem 4c (see
Exhibit 3-31). It was concluded that the TWSC operation would accommodate the fairly low WB left turning volume
(120 vph) with no difficulty. The v/c ratio was 0.56 and the estimated
delay was 41.7 sec/veh, corresponding to LOS E.
-
EB through vs. NB right:
This conflict point was examined as a freeway merge in Sub-problem 4d (see
Exhibit 3-34),
using the procedures from HCM Chapter 25. The resulting density (i.e. the
service measure for freeway merging) was
17.7 pcpmpl,
corresponding to LOS B.
-
NB left vs. WB through:
This is a new merging conflict point created by the flyover as a
substitution for the previous crossing conflict. If the flyover was
designed for a freeway-type merge with an adequate acceleration lane, it
is suggested that the HCM chapter 25 procedure would also be the best
choice for analysis of this conflict point. Assuming the same operating
parameters as the eastbound merge, with a 300 ft acceleration lane from
the flyover, the resulting density is estimated at 8.5
pcpmpl, corresponding to
LOS A.
So, we can conclude that
the construction of a northbound flyover at this intersection would
eliminate the critical conflicts and leave an acceptable operation at the
remaining conflict points. The actual decision to construct a flyover would,
of course, require consideration of many other factors that are beyond the
scope of this analysis.
[
Back ] [
Continue ] to HCMAG Home |
|